India power grid, 2 November: shortage falls to 0.77 MU as October crunch ends

India's unmet electricity demand, the energy shortage, was 0.77 million units (MU) on 2 November. It peaked at 40.5 MU on 6 October. The early-October power crunch is over.

A data update from FactIQ, written from Ministry of Statistics and Programme Implementation India figures. What is FactIQ?

Key figures

India electricity shortage, 2 November
0.77 MUdown from a peak of 40.5 MU on 6 October2026-09-162026-11-02India Energy shortage - All India
India electricity demand met, 2 November
4,775 MUup from 4,614 MU on 1 November2026-09-162026-11-02India Energy met - All India
India highest demand met during the day, 2 November
226,478 MWroughly 258–261 GW peaks around 5–9 October2026-09-162026-11-02India Maximum demand met during the day - All India
India coal-fired generation, 2 November
3,772 MUagainst roughly 4,000–4,170 MU in the first half of October2026-09-162026-11-02India Gross generation, Coal - All India

Shortages have stayed small since mid-October

The energy shortage is the electricity demand that India's grid could not supply. It was 0.77 million units (MU, millions of kilowatt-hours) on 2 November. It has stayed under 3 MU every day since 17 October. Before that, it peaked at 40.5 MU on 6 October and ran at 15–31 MU on most days through 14 October. At the evening peak, when there is no solar power, the shortfall was 269 megawatts (MW).

Demand is well below its early-October level

Energy met, the total electricity supplied to users, was 4,775 MU. That was up from 4,614 MU on Sunday 1 November. The highest demand met during the day was 226,478 MW. Between about 5 and 9 October, daily energy met was about 5,450–5,530 MU, and peaks were roughly 258–261 gigawatts (GW).

Coal plants are burning less fuel

  • Coal generation was 3,772 MU, against roughly 4,000–4,170 MU in the first half of October. This takes pressure off thin coal stocks at power plants.
  • Hydro generation was 322 MU, down from about 345–367 MU a fortnight earlier.
  • Wind, solar and other renewables produced 778 MU, down from a recent high of 938 MU on 28 October. Solar alone produced 628 MU.
  • Total gross generation was 5,203 MU.

More plants are offline, and exports to Bangladesh fell

Plants out of service totalled about 48.6 GW, up from 35–40 GW in mid-to-late October. This probably reflects plants being taken offline for maintenance as demand eases. The Godda plant in Jharkhand, which sells its power to Bangladesh, exported 19 MU. In mid-October it exported about 30 MU. The Frequency Variation Index, which measures grid stability, was 0.10. That is within its normal range.

Source: Ministry of Statistics and Programme Implementation India. See all MOSPI data in FactIQ.

About FactIQ and these updates

  • What FactIQ is. FactIQ is a database of official statistics from government agencies, central banks and international organisations in the US, China, India, Europe and elsewhere. AI assistants such as Claude and ChatGPT connect to it to look up the exact figures and cite the agency that published them. It also holds what companies report in their filings and say on their earnings calls.
  • How an update is made. When Ministry of Statistics and Programme Implementation India publishes new figures, FactIQ loads them and an AI model writes a short summary of what changed. Before it is published, code checks that every number in the summary matches FactIQ's record of the release, and a second review checks that nothing is overstated. Values that look like errors in the source data are left out.
  • Where the numbers come from. Each key figure links to the full series, with its source, units and history.

More about FactIQBrowse the dataUse it in Claude or ChatGPT