India power demand on 23 November: daily peak hits a 30-day high of 234.8 GW
India's peak power demand met reached 234,807 megawatts (MW) on Monday 23 November, the highest in 30 days, as demand picked up after a holiday dip. Power shortages rose but stayed small.
A data update from FactIQ, written from Ministry of Statistics and Programme Implementation India figures. What is FactIQ?
Key figures
- India maximum electricity demand met during the day, 23 November
- 234,807 MWhighest in the past 30 days, above 230,431 MW on 21 November2026-10-072026-11-23India Maximum demand met during the day - All India
- India total electricity supplied (energy met), 23 November
- 4,664.65 MUup from 4,472.38 MU on Sunday2026-10-072026-11-23India Energy met - All India
- India energy shortage, 23 November
- 7.657 MUhighest of the past month, about 0.16% of energy met2026-10-072026-11-23India Energy shortage - All India
- India shortage at peak demand outside solar hours, 23 November
- 2,336 MWprevious 10-day high was 1,466 MW on 19 November2026-10-072026-11-23India all-India shortage at maximum demand in non-solar hours
Electricity use climbed on Monday but stayed below late-October levels
Grid-India publishes daily figures for India's electricity grid. The highest demand the grid met on 23 November was 234,807 megawatts (MW). That was above the 230,431 MW recorded on 21 November. The peak came during solar hours. Energy met measures how much electricity the grid supplied over the whole day, in million units (MU), meaning million kilowatt-hours. It was 4,664.65 MU, up from 4,472.38 MU on Sunday. It was also well above the early-November low of 3,954 MU on 9 November. It is still a little below the roughly 4,770–4,860 MU range seen in late October and early November.
Coal still produced most of the power, and solar output rose
- Total gross generation was 5,120.55 MU.
- Coal produced 3,630.21 MU, about 71% of the total.
- Renewable sources (wind, solar, biomass and others) produced 921.69 MU.
- Solar alone produced 666.77 MU, its highest in at least the past two weeks.
Shortages were the largest in a month but remained minor
The all-India energy shortage, meaning demand the grid could not supply, was 7.657 MU. That was the highest of the past month. It was only about 0.16% of energy met. The Northern Region accounted for 6.77 MU of the shortage. At peak demand outside solar hours, the shortage was 2,336 MW. That was the highest in the past 10 days, above the previous high of 1,466 MW on 19 November. Evening shortfalls in the north are worth watching as winter demand builds, but they are not yet large.